SAT Diving for Spool & Riser installation, Touchdown Monitering, As-Lay Inspection 2023
WORK DESCRIPTION: ROV Pipelay touch-down monitoring,
Pre-Con & Touchdown Survey 2023
WORK DESCRIPTION: ROV Pipelay touch-down monitoring, SAT diving for Spool installation, Riser
SPM Installation, 2023
WORK DESCRIPTION: Installation of 4 x SPM boys at ARAMCO terminal Juaymah Terminal
Removal of test piles 2022
WORK DESCRIPTION:
The second campaign to remove installed test piles used for monitoring seabed conditions
Grab monitoring with ROV to prevent subsea object being damaged during sampling 2022
WORK DESCRIPTION: Grab monitoring with ROV to prevent subsea objects from being damaged during sampling.
Removal of Test piles. Vessel: Horizon Enabler. 2022
WORK DESCRIPTION:
Removal of installed test piles used for monitoring seabed conditions
Helideck Installation 2021
WORK DESCRIPTION: Fabrication & Installation of new helideck including Commissioning after installation:
ROV, Periodic subsea inspection and survey 2021
WORK DESCRIPTION:
Periodic subsea inspection and survey: 2021
ROV, Periodic subsea inspection and survey 2020
WORK DESCRIPTION:
Periodic subsea inspection and survey: 2020
Topside/Rope Access 2019-2020
WORK DESCRIPTION:
Dismantling of helideck on offshore converter station:
Activities relating to the installation of pipeline 2019
WORK DESCRIPTION:
Activities relating to the installation of pipeline:
ROV inspection 2019
WORK DESCRIPTION:
• Project management and planning
• ROV inspection of SPM Buoy
• ROV Inspection Jetty